Turboatom completed the supply of equipment for Starobeshevskaya TPP (Ukraine)

Сентября 30, 2013

OJSC "Turboatom" completed the supply of equipment for the block No 12 of Starobeshevskaya TPP.

In September 2013, the company's specialists have produced and passed under shipping a low-pressure rotor and two, diaphragms of the fourth stage.

Currently on the block No 12 is working on preparing for the installation of a new flow of low pressure cylinder.

On Starobeshevskaya TPP, is realizing a project of modernization of steam turbine K -200 -130 -1 of 200 MW of Leningrad Metal Plant (Russia). Under the terms of the contract signed in October 2011 OJSC "Turboatom" reconstructs the flow of low-pressure cylinder with the replacement of the rotor, diaphragms, clips, gaskets, and the middle part of the body of LPC. After upgrading the capacity of the unit will increase by 8 MW, the efficiency increases to 88%. Completed works will also help to reduce the consumption of fuel by 26.1 g / kWh.

This is the fourth unit Starobeshevskaya TPP, which will update the "Turboatom". Previously, the plant has implemented the reconstruction of block number No 4, 5, 13.

Факты из архива:
На заводе «Алнас» завершается пусконаладка новой литейной линии
Обзор финансовых рынков

Контакты
Адрес: 115114 Россия,
620137 г. Екатеринбург, ул. Студенческая, д. 1 корп. 3
Тел. / факс  (343) 345-09-72
г. Москва, 1-й Дербеневский переулок, д. 5 тел. (495) 287-98-51
E-mail: info@energyland.info
О проекте Powered by <Unknown> engine