Turboatom manufactured cover of hydro turbine for Dniester HPSPP (Ukraine)

Октября 03, 2013

Since this is one of the overall turbine parts, (its weight - 352 tons, diameter - 11 m) , the processing and manipulation of the cover are particularly difficult, so it is divided into four parts.

Welding and machining process of turbine cover took almost ten months. Today the equipment delivered to the customer and shipped to the HPSPP.

To the plant the cover will be assembled in ring on the holder and is mounted on the stator of hydraulic machine.

Also in September by the plant were manufactured and shipped shield and servo of ring valve and seal ring with the details of the guide vanes.

In October "Turboatom" will complete the supply of equipment for the Dniester HPSPP No 2.

For the Dniester HPSPS " Turboatom " produces a reversible Francis turbine ORO 170 -B -730 with maximum capacity in turbine mode of 390 MW, in the pump - 420 MW. The uniqueness of the hydraulic units is that they work in the "pump - turbine" mode and allow the use of accumulated at night hydropower for electricity manufacture during peak loads on the network (busy schedules of consumption).

Контакты
Адрес: 115114 Россия,
620137 г. Екатеринбург, ул. Студенческая, д. 1 корп. 3
Тел. / факс  (343) 345-09-72
г. Москва, 1-й Дербеневский переулок, д. 5 тел. (495) 287-98-51
E-mail: info@energyland.info
О проекте Powered by <Unknown> engine