Those resources will be used to improve reliability of electric power supply system in the city of Sochi by connection of distribution networks of Kubanenergo JSC. Currently, the deferred demand under the contracts which performance was postponed due to the state moratorium on connection of new consumers, is 281.2 MW.
FGC UES has discussed plans for using the power infrastructure of Sochi with the stakeholders. It’s been seven years that FGC UES is publishing a Social Responsibility and Corporate Stability Report. The Report covers main results of the company performance and management approaches adopted in the economic, social and environmental fields. The Report structure is successive compared to previous years, which allows comparing data over different periods.
The company had implemented a unique project in terms of its scale and complexity – preparation of the Sochi power infrastructure for the Olympics. That is why the section called “Power supply system for the Olympics and usage of the developed power structure after the Games are over” was the key topic of the Report.
Altogether, in 2013 FGC UES has commissioned 11 thousand MVA of transformer capacities and 3.5 thousand power transmission lines. During the preparation of the Sochi power district for hosting the Winter Olympics and Paralympics Games, 36 facilities were constructed and upgraded including 13 greenfield facilities, as well as 326.6 km of lines and 14 substations of the total capacity of 1715 MVA. FGC UES has invested 18.6 bln rubles in construction and modernization of the above facilities.
Over 110 Olympic facilities of the total capacity of 397,5 MW were connected to the electric power networks of the company. Trouble-free operation of the power infrastructure was assured including peak demand periods. Maximum design load on the electric networks during the Olympics was 661 MW (the absolute maximum value is 683 MW). In 2008, the same figure amounted to 480 MW, and in 2012, it was 559 MW.
См. также:
Компания «Газпром нефтехим Салават» смонтировала блок удаления кокса
Курс на энергосбережение: что надо поменять
Правило Legrand: современный офис – это эффективное освещение каждого квадратного метра