By the results of functional and oil tests, the Acceptance certificate was signed. Then the runner will pass balancing and will be shipped to the station, after that, the contract will be closed in the production.
The project of the modernization of horizontal bulb hydraulic turbine with the installation of new runner and guide vane is realized at Kanevskaya HPP. During the modernization new high-performance Kaplan-type runner with the diameter of 6 m with updated blading will be installed and the guide vane equipped with new blades with improved profile to be installed at the hydraulic power plant as well. After the reconstruction the capacity of hydraulic unit is expected to increase from 19,2 MW to 23 MW, the efficiency is likely to increase by 4%, the reliability and service life of the turbine are expected to increase as well.
The scope of obligations of "Turboatom" also includes supervision installation and pre-commissioning technical manual.
The start-up of the unit is planned at the end of the 2014 year.
Currently, with the participation of erection supervisors of the enterprise the guide vane is being erected, after that, there will be erected the runner and other units of hydraulic turbine.
24 hydraulic turbines manufactured by OJSC "Turboatom" are installed at Kanevskaya HPP. Today, after the reconstruction 12 turbines are commissioned, 1 turbine is being pre-commissioned and 1 turbine is being erected.
В котельном цехе Южно-Кузбасской ГРЭС смонтировали новый двухбалочный мостовой кран
Медицинский комплекс во Владивостоке к 2015 году получит 1 МВт электрической мощности
В Санкт-Петербурге пройдут обучение более 400 работников бюджетной сферы