The specialists of the enterprise carried out check assembly of the equipment providing installation of extreme tube boards plated by titanium. Thereafter stuffing of modules with titanic tubes, its rolling and welding will be executed. The equipment will be packed and shipped to the station after performing control of weld joints by the dye penetrant flaw detection method and pneumatic tests
It is planned to complete work on the condenser in August of the current year after executing check assembly and handing over to the customer modules of the third condenser case.
The contract for the supply of a condenser for the power unit No. 4 of Rostovskaya NPP under construction was signed in December 2011.The term of delivery is the year 2014.