Erection and starting-up and adjustment works were implemented with participation of supervision-engineers and specialists of the enterprise.
During successful 72-hours comprehensive testing functionality of turbine, equipment and auxiliary systems was confirmed.
Next stage of program of power commissioning of Unit No 3 Rostov NPP will be reaching of capacity from 35% up to 50%, then reaching rated capacity 100% and implementation of acceptance testing. Commercial operation of Unit No3 supposed for July 2015.
This is 19th commissioned low-speed turbine К-1100-60/1500 with capacity 1000-1100 MW, manufactured by "Turboatom".
At three Units of Rostov NPP erected turbines manufactured by OJSC "Turboatom" with unit capacity 1 mln. kW. At present moment the enterprise works on manufacturing of the 4th turbine, part of equipment is under erection.