In presents of customer functional, oil, strengthen and hydro tests were held. Parties signed Acceptance Certificate stated that all controlled parameters are in accordance with requirements and accepted by customer. Further this equipment will be packed and provided for shipment. At this moment in manufacturing are distributor, shaft and other mechanisms of hydroturbine.
Under contract, concluded in July 2011, OJSC "Turboatom" implement rehabilitation of three Kaplan type hydroturbines with rated capacity 58 MW with change of runners with diameter 8 m, shafts of hydroturbines, guide vanes and bearings. As a result of implemented works capacity of every unit will increase up to 64 MW. Also will increase life time and overhaul period of equipment.
Terms of delivery of the first turbine – 2014, the second – 2015, the third – 2016.