30 Ноября 2024 | суббота | 15:26
Energoterra

Stroytransgaz will build gas pipeline branch under contract with Gazprom investgazifikatsiya

Марта 02, 2015

CJSC Stroytransgaz entered into an agreement with Gazprom investgazifikatsiya LLC to build gas supply facility Gas pipeline branch from a tie-in point into main gas pipeline Bovanenkovo – Ukhta up to Gas Distribution Station-2 of the city of Pechora.

The gas pipeline branch will be built as a part of the project to extract crude hydrocarbons from filed deposits of OJSC Lukoil in the republic of Komi to be processed at the Sosnogorskiy gas processing plant and to provide continuous gas supply for consumers of the Pechorskiy industrial hub.

The facility length will make 17.3 km; the pipe diameter will be 325 mm, the wall thickness – 11 mm.

As a part of the project there will be built an in-tube unit launcher and a gas disposition terminal, roads and pipelines, diameter from 150 mm to 1,400 mm, will be crossed, a winter motor road will be specially equipped.

The works will commence in December 2014 and end in the middle of March 2015.

Контакты
Адрес: 115114 Россия,
620137 г. Екатеринбург, ул. Студенческая, д. 1 корп. 3
Тел. / факс  (343) 345-09-72
г. Москва, 1-й Дербеневский переулок, д. 5 тел. (495) 287-98-51
E-mail: info@energyland.info
О проекте Powered by <Unknown> engine