During the month 1012 meters of coal were completed.
In fact the crew did the record meter in 22 days – from 7th to 28th of February. In one of those days the daily record was set – 78 meters. A daily average fore-head output was 46 meters.
The team managed to achieve such record loads through the effective use of high-performance Sandvik MB670 combined with wide drum working body and mounted rigs. At the same time, the mining and geological conditions of preparation of the drain drift are quite complex - large influx of water, angle of 17 degrees, "false" roof in the form of siltstone.
- The main component of success - is teamwork and solid focus on achieving kilometer results - said the section chief Igor Savintsev. – There are 37 people in brigade, including three of our new colleagues from the Donbass. In February, we worked with 11 interns and trainees from Kiselevskoye and Prokopyevsky Mining Colleges. Most attention was paid to the strict observance of work safety. And we did it.