Condenser was assembled without cooling pipes, they supposed for installation at plant. Next equipment will be packed and provided for shipment.
At this moment plant works on manufacturing of High, Middle, Low Pressure Cylinders and Regulating System.
In accordance with the contract, concluded in June 2014 OJSC “Turboatom” developed design, project and technical documentation and also manufacture and supply two steam turbines К-330-23,5 in full set for rehabilitation of Unit No 6 Slavyanskaya TPP. Moreover plant will make supply of auxiliary equipment and spare parts. Obligations of enterprise also include supervision of erection and field supervision.
Commissioning of Units with new turbines planned for: Unit No 6б in March 2017, Unit No 6а – in March 2018.
Works on preparation for rehabilitation of lay up Unit No 6 Slavyanskaya TPP were since August 2013. Unit will be divided into two units with capacity 330 MW each using technology of coil burning in circulating boiling bed (CBB).
Slavyanskaya TPP was first Power Plant in Europe and Soviet United where in 1963 were installed Units with capacity 800 MW for supercritical steam parameters. Slavyanskay TPP has in its structure of operating equipment one Unit No 7 with capacity 800 MW.
Plant situated at North of Donetsk region on left bank of Severskiy Donets river.