Currently, the preparations for the strength and tightness of the pipeline, including the industrial pipeline welding process and connection of the receiving-start chambers of the cleaning and diagnostics tools, and the construction of pits for water drainage are being held.
The length of the third phase linear part is 151.5 km. The hydraulic testing will be conducted one after another on two sites (0-87.2 km and 87.2 – 151.5 km) of the pipeline. It is scheduled to start filling the pipeline sections with water on July 1, 2015. It is expected that all the works on the hydraulic testing will be completed within a month.
Currently, there are also the preparations for hydraulic testing of the main and redundant threads on the oil trunk pipeline underwater crossings through the Pur and Taz rivers.