Turn-key renovation agreement for three hydro power units of the oldest Latvia HPP, Kegums-2, was concluded in February 2014. The agreement conclusion was preceded by a tender won by Power Machines with the best technical and economic solution.
The Power Machines scope of supply and services comprise fulfilling of design works, manufacturing and supplying of equipment, renovation of three plant’s hydro power units. Power Machines will manufacture and deliver three new hydro power units with maximum capacity of 77.8 MW (15 m drop) each, completed with automated control systems (ACS), as well as equipment for renovation of three hydro power units. Besides, Power Machines shall perform engineering, commissioning and performance acceptance testing of the hydro power units followed by further commissioning.
Due to renovation the Kegums-2 HPP units will comprise modern hydro equipment with enhanced specifications and reliability.
Renovated units are scheduled for commissioning in 2016–2018.
Earlier in 2013 Power Machines won tender and concluded a turn-key renovation agreement with AS Latvenergo for hydro power units No. 1 and No. 3 of the Pļaviņu HPP. As a result of the renovation, each power unit’s capacity shall be increased by 14 MW, from 82.5 MW to 96.5 MW. Renovated units are scheduled for commissioning in 2016–2017
См. также:
Ростехнадзор привлек к административной ответственности «Нефтегазстройсервис»
В Лучегорске прошли соревнования оперативного персонала ТЭС ОАО «ДГК»
По вине чиновников школы и детсады остаются без горячей воды
Для чего необходим автотрансформатор
Ежегодное обслуживание воздушного кондиционера
Техника для лесной отрасли
О выставке «Безопасность и охрана труда»