It’s the part of the Southern Corridor gas pipeline system, Western route.
The Customer of the project is Gazprom Tsentrremont LLC. The General Contractor is LLC «StroyGazMontazh», the Subcontractor is Krasnodargazstroy JSC.
During modification of the Pisarevka CS the 3d compressor shop has been constructed and equipped with 7 units of 16MW GPUs. Thus, the capacity of the station has increased by 112 MW.