In presence of customer equipment passed control assembly with check abutment horizontal outer connectors and internal casings of cylinders clips seals, diaphragms, seals casings and other parameters. According to results of tests was signed acceptance protocol.
Under conditions of the contract signed in June 2014 PJSC "Turboatom" developed design, project and technical documentation, as well as manufacture and supply two steam turbines K-330-23.5 with full packaging arrangements for reconstruction of Unit No 6 Slavyansk TPP. In addition, plant has supplied accessories and spare parts. Obligations of enterprise also include supervision of erection and field supervision.
Preparatory work for reconstruction of put out of service Unit No6 Slavyansk TPP conducted from August of 2013. The power unit will be divided into two Units with capacity of 330 MW each.