Power Machines have implemented design, supply, installation, and commissioning of turbine island equipment within the scope of this power unit.
The scope of equipment supplied to one power unit includes the K-660-247 turbine operating at supercritical steam parameters, manufactured at the Leningradsky Metallichesky Zavod, the TVV-660-2TZ turbine generator manufactured by the Electrosila plant, as well as two K-14-2.0P drive turbines manufactured by Kaluga Turbine Works.
Equipment for power units No. 2 and No. 3 was also manufactured and fully delivered to the TPP construction site by Power Machines. Commissioning is scheduled for 2022.