The project is executing within the limits of the contract of technological connection of OJSC «Gazprom Invest Zapad» to electric networks of «Vologdaenergo» branch. According to the contract the Grid company undertakes to reserve total capacity 2800 kWt on the power supply.
For realisation of an external electrical supply of compressor station «Novoyubileynaya» of the main gas pipeline «Ukhta-Torzhok» on substation 110/35/10 kV «Pogorelovo» two new cells 10 kV type K-63 with vacuum switches will be established.
Now the works executor – «Vologdaenergomontazh» ltd has delivered necessary equipment on substation territory. It is planned to finish works on installation and adjustment of new cells by the end of April, 2010. Service cost as per contract will equel 5,2 million roubles.