At presence of inspectors of Mexico laboratory on execution of all kinds of tests (LAPEM) runner was balanced, geometry test, DPT and SST of welding. Under results of test parties signed appropriate protocol. Equipment was manufactured in accordance with agreement requirements and shipped to customer. In manufacturing contract fully finished.
Also under terms of the contract "Turboatom" will carry out supervision of erection, balancing and commissioning and actual tests.
At the present moment on HPP site erection and concreting of embedded parts of the first hydraulic unit was finished.
Commission of the first turbine appointed for February 2012, second – May 2012. During two years guarantee period will be valid, after this plant will come into commission of active Mexico HPP. General rated capacity of La Yesca HPP will be 750 МW.
Contract for manufacturing of equipment for plant was signed in March 2008. In accordance with agreement plant manufactured two hydroturbines with unit capacity 380 МW with built-in ring valves.