During the visit the guests familiarized with the steam-turbine and hydro turbine production in the workshops № 53, № 83 and held talks on the prospects of energy cooperation.
At the talks dealt with the participation of "Turboatom" in the completion of the block № 3 Ekibastuz TPP-2 capacity of 580 MW. OJSC "Turboatom" offered customers a new generation of turbine, operating at supercritical steam capacity of 580-600 MW. According to the agreement for participation in tender which will be held in November this year "Turboatom" would prepare a techno-commercial proposal. Enter the unit is scheduled for the fourth quarter of 2013. According to the manual JSC “Samruk-Energo» in the future construction of five more units Ekibastuz TPP-2.
Also considering the possible involvement of "Turboatom" in the supply of equipment for HPP and NPP, construction of which provides national program of power engineering development of Kazakhstan.