At Tolmachevsky HPP-2 began commissioning works involving specialist of OJSC "Turboatom"

Октября 25, 2010

Specialist of OJSC "Turboatom" went on Tolmachevsky HPP-2 (Russia) to accompany starting-up and adjustment and commissioning of the plant.

In July 2008 OJSC “Turboatom" dispatched 2 butterfly hydro valves with diameter of 1,4 m, the static pressure of 175 m for the building Tolmachevsky HPP-2. At the moment, has already completed supervise erection of equipment, and conducted starting – up and adjustment-led Design engineer of OJSC “Turboatom” Boris Geshenzona.
Tolmachevsky HPP-2 installed capacity of 24.8 MW is part of a cascade of small Tolmachevsky HPP, located in the Kamchatka region, the river Tolmacheva.