The document was signed by the Chairman of the Management Board of JSC FGC UES Oleg Budargin and General Director of OGK-4 Yuri Sablukov.
Interaction shall be implemented in accordance with Plans-schedules of events by synchronization of investment programs of the companies regarding input of generating capacities and construction of electric grid objects to output electric power to UNEG.
At the present time corresponding schedules were acceoted within the Agreement regarding investment projects in comissioning of new generating capacities and synchronized electric grid construction of power units No. 7 and 8 of Surgut power station-2, power unit No. 5 of Yayvinskaya power plant and power unit No. 3 of Berezovskaya power plant.