Equipment will be installed at the second power generating unit of the thermal power plant that is constructed within the scope of investment project of JSC «TGK-1».
The Contract has been signed in October, 2010 and stipulates delivery of the transformer rated for 250 MVA, 110 kV and two transformers rated for 250 MVA, 330 kV to JSC «TGK-1». The advance payment has been already received, and the order is distributed into production. Shipment of all three units is scheduled for the 2nd quarter of the year 2011.
Construction of a new power generating unit of TPP-5 Pravoberezhnaya belongs to priority project related to investment programme of JSC «TGK-1» for the period up to the year 2015. Generating capacity of the 2nd power unit, constructed in correspondence with up-to-date combined-cycle technologies, constitutes 450 MW, thermal capacity – 350Gcal/hour.