The gas pipeline branch has been laid for further gasification of Tambov region and supply of gas to a sugar mill under construction.
The gas pipeline branch is 28 km long, 273 mm OD, 5.4 MPa operating pressure.
CJSC “Gazprom invest Yug” is the Client and LLC “Gazprom transgaz Saratov” is the operating entity.
Tokarevka – Mordovo gas pipeline branch construction was commenced in November 2009 and completed in November 2010.