The average cost of work amounts to 2.4 bln rubles.
The project is technically aimed at the power distribution of energy block No. 4 of the Kalinin nuclear power plant via Belozerskaya Substation in the Cherepovets region of the Vologda Oblast. The FGC UES subsidiary BPS Center is the customer of the project.
Within the frames of the project 82.2 kilometers of one-chain and two-chain 220 kV HV lines will be constructed, the existing HV lines 10\35\110\220\500 kV of the total length 6.15 kilometers will be reconstructed, one-chain 220 kV HV line Energia-3 of the total length 16.2 kilometers will be dismantled. Besides that, 220 kV Indoor Switchgear will be constructed and RPP1 Substation in Cherepovets will be partially reconstructed.
Stroytransgaz scope of work will include working documentation, equipment delivery and construction of the stated facilities.
Within the frames of its production activities diversification, Stroytransgaz has been working since 2006 in the energy construction market. Under order of FGC UES, Stroytransgaz realizes some power grid projects as a general contractor, including the construction of power distribution facilities for energy block No. 4 of the Kalinin nuclear power plant, and the construction of 500 kV HV line Boguchanskaya hydro electric power plant–Ozernaya Substation.
Stroytransgaz’ business portfolio in the power grid facilities construction sector at present exceeds 50 bln rubles.