The pipeline – branch and the gas distribution station (GDS) are put into operation in the town of Puchezh

Декабря 22, 2010

LLC “STROYGAZMONTAZH” has completed construction of the pipeline-branch and the GDS in the town of Puchezh (Ivanov region).

The pipeline length amounts to 26 km, the pipe diameter is 325 mm, the operating pressure - 5,4 МPa.
The construction was ordered by CJSC “Gazprom invest Yug”. The operating company is LLC “Gazprom Transgaz Nizhniy Novgorod”. The main contractor under this project is OJSC “Volgogaz”.
The construction of the pipeline – branch and the GDS commenced in February and was completed in December 2010.