In accordance with the contract Sumy Frunze manufactured seven turbocompressor packages and station equipment used for process gas reducing, heating, as well as fuel gas purification for Saveh gas compressor facilities. The equipment was manufactured and shipped during a year.
Besides this within the framework of this contract Sumy specialists carried out supervision of erection and commissioning at the site.
In general Saveh compressor station was building during three years. It can transfer up to 160 million cubic meters of natural gas per day. Therewith, by means of this station natural gas will be simultaneously transferred in three directions to the Central, North and North-West parts of Iran.
JSC «Sumy Frunze NPO» has long-term partnership relations with Iran. Sumy Frunze helped to build a lot of objects of gas-transport system in this country such as: Hadjiabad, Khavaran (the first and the second phases), Parsian, Abshirin, Sirjan, Abade gas compressor facilities and many others.