During the tests, plant specialists check the efficiency of the blade on the identity of the reversal of blades, as well as the level of pressure. As a result of the work was signed by the act of acceptance of equipment that all the controlled parameters correspond to the norms. Further, the blade will be balanced on the stand of 83r workshop.
It is completed manufacturing of the shaft of the blade Dneprodzerzhinsk HPP. Until the end of February equipment planned to be shipped to the customer.
At Dneprodzerzhinsk HPP (Ukraine) as part of the renovation project plants of Dnepr cascade “Turboatom” updates turbine equipment. Previously for this plant plant delivered parts of the wicket gate, blade chamber, the guide bearing and the mechanisms of the turbine.