Total length of the gas pipeline “Onshore Production Facility of Kirinskiy gas condensate field – Head Compressor Station Sakhalin” is - 136,7 km. Pipe diameter is - 1020 mm, pressure - 9,8 MPa, design productivity - 4,25 billion m3 of gas per year.
Project implementation period under the contract is: the 2nd quarter of 2011 – the 3rd quarter of 2012.
LLC “SGM” specialists have proceeded with preparatory works: relocation of machinery and arrangement of rotators' camp for reception of builders and engineering – technical specialists in Nogliki settlement of Sakhalin area are being performed.
LLC “Stroygazmontazh” has already had the experience in working in the Far East. The company is a general contractor of OJSC “Gazprom” in construction of gas transportation system Sakhalin – Khabarovsk – Vladivostok, on which LLC “Stroygazmontazh” is responsible for construction of 540 km out of 1350 km (the first start up complex).
At the present time over 85% of the project have been already implemented: more than 460 km of the gas pipeline have been welded into a string and back filled. It is planned that the gas pipeline Sakhalin – Khabarovsk – Vladivostok will be handed over to employer already in the 3rd quarter of this year.