Currently, all the equipment for the installation of transformer substation110 kV is delivered to the site. It is planned that next week the contractor will start assembling of metal constructions. In addition, at the object were delivered traverses for installation of steel portals.
To complete the reconstruction of the substation, “Vologdaenergo” plans by the end of 2011. Capital investment in the project will be about 199 million rubles.