“IDGC North-West” completes the reconstruction of substation 150 kV that provides electricity to the Kovdorsky ore –dressing enterprise in the Murmansk region

Июня 23, 2011

At the substation 150 kV of “Kolenergo”, which supplies electricity to the city Kovdor and Kovdorsky ore –dressing enterprise , was completed reconstruction with the installation of the batteries of the static condensers.

The reconstruction will increase the capacity in the network 6 kV substation-40A at 20.4 MVA, will give the possibility to maintain the desired voltage level, to improve the quality characteristics of the transmitted power and to ensure the reliability of electricity supply to consumers.
Costs of “Kolenergo” for the reconstruction of the object in 2010-2011 amounted to 18, 2 million rubles.

Контакты
Адрес: 115114 Россия,
620137 г. Екатеринбург, ул. Студенческая, д. 1 корп. 3
Тел. / факс  (343) 345-09-72
г. Москва, 1-й Дербеневский переулок, д. 5 тел. (495) 287-98-51
E-mail: info@energyland.info
О проекте Powered by <Unknown> engine