TGC-1 has set new equipment at Putkinskaya HPP in Karelia

Января 28, 2012

GC-1 has finished the large project of refurbishment three units' speed control at Putkinskaya HPP (Kem' HPPs Cascade) in Karelia.

TGC-1 has finished the large project of refurbishment three units' speed control at Putkinskaya HPP (Kem' HPPs Cascade) in Karelia.

Within the project there was installed the system of total control of the active capacity that allows to manage all the hydraulic units of the plant. Automatic regulation increases the presiseness of parametres and gives an opportunity to watch the equipment quality.

Setting new modules means also growing of safety and efficiency of the plant as well.