The equipment supply contract was concluded in June 2011. Under the contract EMAlliance undertook the supply of HRSG of about 2300 tons for CCP-50 of Permskaya TPS-9. Equipment design was made by the specialists of PJSC Engineering Centre EMAlliance – BSDB BP (Barnaul). The equipment is manufactured by Taganrog Boiler Making Works Krasny Kotelshchik under the licence of American company NOOTER/ERIKSEN, INC. The works are planned to be completed untill the end of July 2012.
HRSG with the specific reburning device under Permskaya TPS-9 reconstruction project is manufactured for the first time. The application of this technology will ensure HRSG stable steam parameters in all operating modes of gas turbine, as well as more effective natural gas usage than while burning it in traditional steam boilers. The specified burners and gas distributing grid, which will be installed in gas inlet duct, will increase equipment steam capacity.
Under investment program realization IES-Holding will purchase 5 HRSGs for new power units from PJSC EMAlliance. Contract terms and conditions provide the development of technical documents, complete equipment manufacture, supply, errection supervision and pre-commissioning works. HRSGs will be a part of new combine cycle plants on Permskaya TPS-9, Kirovskaya TPS-3, Izhevskaya TPS-1, Novobogoslovskaya TPS, Vladimirskaya TPS-2.