Eesti Energia lays cornerstone for Auvere power plant

Мая 14, 2012

The cornerstone for a new power plant was laid. The new power plant will be completed by the end of 2015 and will be called Auvere power plant. The generating capacity of the plant is rated at 300 MW.

"Estonia has opted for energy independence and for covering its basic demand using domestic generating capacities. Auvere power plant is being established in the interests of guaranteeing reliability of the national power supply and it will have a key role in ensuring energy independence," said chairman of the Eesti Energia management board, Sandor Liive, at the cornerstone laying ceremony.

Compared to the existing oil shale-fired power plants, Auvere power plant will be more environmentally friendly, with lower emissions and greater efficiency. The construction of the power plant will provide work for 1,000 people and the completed plant will create 120 new jobs. At the moment, 120 construction workers are employed at the site.

Auvere power plant will use oil shale as its fuel and it can be up to replaced up to 50% with biofuel. "To raise Auvere power plant's competitiveness amid conditions of stringent climate policy, we provided for the option of using biomass. Substituting biofuels for oil shale will cut Auvere power plant's CO2 emissions to that of modern, efficient natural gas installations, hedging CO2 price risk and making the plant more competitive in the event of a high carbon credit price.

Use of a local fuel will hedge the fuel price risk. Auvere power plant will ensure sufficient flexibility for Estonian power generation, as it is capable of generating power at times when it is needed.

The Estonian government is continuing talks with the European Commission for financing the construction of Auvere power plant via free CO2 allowances. The European Union has acknowledged Estonia's need for new power generating capacities and EU legislation allows companies to be given free CO2 allowances, which are invested into new production capacities.

Eesti Energia announced the public procurement for a fluidized bed boiler technology based power plant in 2009. The best tender proved to be the one from the Alstom consortium. The contract for the construction of the power plant was signed in January 2011. The cost of the new power plant is close to 640 million euros.

Along with the Enefit280 oil plant to be completed this year, Auvere power plant will be a part of a modern energy complex sharing an oil shale storage facility, fuel feeder system, ash processing system and a new 330 kV power distribution station.

Контакты
Адрес: 115114 Россия,
620137 г. Екатеринбург, ул. Студенческая, д. 1 корп. 3
Тел. / факс  (343) 345-09-72
г. Москва, 1-й Дербеневский переулок, д. 5 тел. (495) 287-98-51
E-mail: info@energyland.info
О проекте Powered by <Unknown> engine