Under the contract "Turboatom" will implement the replacement of two condensers for turbine feed pumps (TFP) of turbine installation with capacity of 500 MW on condensers of block-module implementation with stainless pipe systems.
The main innovation of condensers is the cooling tubes and the outer tube plates from stainless steel. The new design will allow avoiding the complexity of water-chemical regime and prolonging operation life.
The scope of the obligations of the enterprise includes the design, manufacture and delivery, followed by supervises erection, participation in the starting-up and adjustment and commissioning of the equipment.
The plant has three operating power units, it provides Voronezh region by electricity on 85% and the city Novovoronezh (Voronezh region) by heat on 50%.